16 projects were found under "Office and Administrative Infrastructure". (Select another Defence Capability Investment Area).

Project Funding Ranges Definition Approval Implementation Approval Initial Delivery Final Delivery Project Sponsor
21 Electronic Warfare Regiment - CFB Kingston $20 million to $49 million Completed Completed 2025/2026 2025/2026 Assistant Deputy Minister (Infrastructure & Environment)
Accommodate 4 Engineer Support Regiment - Gagetown $100 million to $249 million Completed Completed 2023/2024 2024/2025 Assistant Deputy Minister (Infrastructure & Environment)
Accommodate 430 Tactical Helicopter Squadron - Valcartier Under $20 million Completed Completed Completed 2022/2023 Assistant Deputy Minister (Infrastructure & Environment)
Canadian Special Operations Regiment - Equipment (Phase 1 and 2) $100 million to $249 million Completed Completed Completed 2025/2026 Canadian Special Operations Forces Command
Canadian Special Operations Regiment Infrastructure $250 million to $499 million Completed Completed Completed 2023/2024 Assistant Deputy Minister (Infrastructure & Environment)
Canadian Special Operations Training Centre Infrastructure (CSOTC) - Petawawa $250 million to $499 million 2024/2025 2026/2027 2031/2032 2032/2033 Assistant Deputy Minister (Infrastructure & Environment)
Construct Community Recreation Centre - Wainwright Under $20 million Completed Completed Completed 2022/2023 Assistant Deputy Minister (Infrastructure & Environment)
Construct New Facility For 2 Service Battalion's Administration Company and Forward Support Group - Petawawa $20 million to $49 million Completed 2024/2025 2024/2025 2024/2025 Assistant Deputy Minister (Infrastructure & Environment)
Construct Royal Canadian Dragoons (RCD) Bldg/ IPD - Petawawa $50 million to $99 million Completed Completed Completed 2023/2024 Assistant Deputy Minister (Infrastructure & Environment)
Construct Transition Centre - CFB Gagetown Under $20 million Completed 2022/2023 2024/2025 2024/2025 Assistant Deputy Minister (Infrastructure & Environment)
Fleet Maintenance Facility Cape Breton Shop Consolidation - Esquimalt $500 million to $1 billion Completed Completed Completed 2022/2023 Assistant Deputy Minister (Infrastructure & Environment)
Future Combined Aerospace Operations Center Capability (NORAD modernization) $1 billion to $4.99 billion 2027/2028 To be determined 2030/2031 2032/2033 Royal Canadian Air Force
Headquarters Shelter System (HQSS) $100 million to $249 million Completed Completed Completed 2022/2023 Canadian Army
House 5 Combat Engineer Regiment - Valcartier $50 million to $99 million Completed Completed Completed 2022/2023 Assistant Deputy Minister (Infrastructure & Environment)
Joint Task Force 2 Infrastructure $1 billion to $4.99 billion Completed 2022/2023 2033/2034 2033/2034 Assistant Deputy Minister (Infrastructure & Environment)
National Defence Secure Campus $1 billion to $4.99 billion 2025/2026 2028/2029 2032/2033 2033/2034 Assistant Deputy Minister (Infrastructure & Environment)